Twelve years of nitric acid plants — diagnosed, designed, revamped and supplied.

Every project below is described the way another plant would want to read it: what the problem was, what we changed, and what it did to the energy balance.

SINCE 2014

The thread that runs through all of it

Since 2014 ARCET has handled process catalyst procurement for a large number of nitric acid plants. That work was never only purchasing.

Every campaign arrived with its own problem — a gauze burning unevenly across the basket, a DeNOx bed losing activity faster than it should, a plant that could not hold its permit through start-up. Solving those meant going back into the catalyst design itself: pack composition, bed geometry, and the operating window the catalyst had been specified against in the first place.

That is where the rest of this page comes from. Twelve years of watching what actually happens on the gauze, in plants we did not build, is why we now design the plant around it.

Since2014, continuous
ScopeProcess catalyst procurement for nitric acid plants
Beyond supplyActive role in catalyst design changes
Driven byPlant problems and operating limits, not a catalogue
PlantsMultiple, in Türkiye and abroad

PROJECT RECORD

Selected projects

2019–2022 · Türkiye · Nitric acid plants

Tail-gas DeNOx systems — design, procurement and manufacturing

Delivered on more than one line. Scope covered the DeNOx catalyst, the reactor module and its vessel, through commissioning and operator training.

Completed

2020 · Türkiye · Nitric acid plant

Plant fault diagnosis

A recurring problem the operator had not been able to close. We rebuilt the whole flowsheet from the plant's own data — process flow, heat balance and material balance — and traced the fault to its source rather than to its symptoms.

Completed

2021 · Türkiye · Nitric acid plant

Revamp and upgrade engineering for capacity increase

Converter internals, expander gas heater, N₂O and NOx abatement, and colourless start-up and shutdown.

Completed

2022 · Türkiye · Nitric acid plant

Platinum recovery filtration — design, procurement and manufacturing

Vessel and filter mesh within scope, delivered through commissioning and operator training.

Completed

2024 · Türkiye · Nitric acid plant

Licence and proprietary equipment — 40% capacity increase

Reactor, expander gas heater, N₂O and NOx abatement combined in a single vessel, and colourless start-up and shutdown. Commissioning and training included.

In progress

2025 · Türkiye · Nitric acid plant

Reactor replacement study — capacity and N₂O together

Feasibility for a reactor change serving a capacity increase and N₂O abatement at once, framed by the operator's corporate zero-carbon target.

Completed

2025 · North Africa · Nitric acid plant

Relocation, refurbishment and revamp with capacity increase

Full scope through installation and commissioning, continuing into supervision of plant management after start-up.

In progress

2026 · North Africa · Ammonium nitrate plant

Greenfield ammonium nitrate plant — EPCM

Appointed as EPCM contractor for a new ammonium nitrate plant from greenfield. Basic engineering is under way.

In progress

WHAT THE LIST IS SAYING

Read down the scope column

Diagnosis. Engineering study. Licence. Proprietary equipment. Catalyst supply. Relocation. Installation. Commissioning. Plant management. All in one list, for one plant type.

Most companies in this business do one of those things. Doing all of them changes where the engineering starts — because the same people who draw the heat balance are the ones standing in the control room at start-up, having to make the number true.

It is also why we resist selling a configuration before seeing a plant's data. The cheap answer and the right answer are rarely the same, and only one of them is still cheap in year five.

Plant typesNitric acid, ammonium nitrate
GeographyTürkiye, North Africa
Delivery modelsStudy, licence, equipment supply, EPCM
Recurring themesCapacity increase, N₂O and NOx, energy balance
Client namesWithheld by agreement
Scope by year on nitric acid and ammonium nitrate plants: diagnosis, engineering study, licence, proprietary equipment, catalyst supply, relocation, installation and commissioning, plant management and EPCM

The same record, read as scope rather than as dates. Every row is drawn from the projects listed above.